| Task | Start | Duration |
| Installation Phase | ||
| Prototype Integration Tests | now | to fall 04 |
| New Round of Simulation Studies | May 04 | to install. |
| ADF v.2 Available | Oct 04 | |
| Long-term Integration Tests Collect Splitter Data |
Oct 04 | to install. |
| Develop Calibration & Testing | Dec 04 | to install. |
| System Infrastructure to Test Area | Jan 05 | to install. |
| Installation Phase [1] | ||
| Tevatron Shutdown (sets start point for all following tasks) |
Jul 05 (?) | 14 w (?) |
| Remove Old Racks | 1 w | |
| Redress Cables | 2 w | |
| Install Racks | 0.2 w | |
| Connect New Rack Services | 1 w | |
| Connect BLS & Intermediate Cables | 1 w | |
| Technical Commissioning | 4 w | |