13-Apr-04 ************************************************************ DRAFT RUN IIB L1CAL PRE-OPERATION RESPONSIBILITIES DRAFT ************************************************************ L1CAL READINESS VERIFICATION ============================ 1) Data Collection using the Test System Includes running the system in as steady-state a mode as possible with as many split signals and as much hardware as is available, ensuring that data is written to tape, performing specific tests as necessary Groups UIC (lead), Columbia, MSU Comments more effort would be helpful here 2) Downloading Includes designing and implementing an efficient scheme for downloading firmware and all required parameters to all cards in the system Groups MSU (lead), Northeastern, Columbia, Saclay 3) Online Monitoring Tools Includes development of online monitoring for l1Cal Groups MSU (lead), Northeastern, Columbia 4) Parameter Determination Includes development of methods for efficiently determining system parameters such as digital filter coefficients, thresholds, etc., both online and offline methods will be required Groups MSU (coordination), Columbia Comments more effort (leadership?) is needed here 5) Integration with Trigger Framework Includes adding Run IIb L1Cal and/or inputs to TFW for Test System and final configuration, other changes to TFW for Run IIb L1Cal Groups MSU 6) Unpacking/Reco/Examines Includes implementing unpacker and examines for L1Cal, testing stability of the code Groups FSU 7) Simulation Framework Includes implementing L1Cal algorithms in tsim, overseeing generation of appropriate MC data samples Groups Northeastern (lead), Rice, Saclay 8) Simulation Verification Includes verification of MC QCD samples using Run IIa data Groups ??? Comments help needed 9) And/Or & Trigger Terms Includes determination of optimal and/or and trigger terms through MC study, inclusion of trigger terms in trigger list Groups Northeastern, Rice, Columbia Comments more effort probably required 10) L2 and L3 Triggers Includes modifications to L2 and L3 triggers necessary for inclusion of Run IIb L1Cal Groups ??? Comments help needed 11) Studies of Splitter Data Includes comparison of ADF Et(TT) with precision readout and Run IIa L1Cal, determination of correction factors to be applied to MC modeling of Et(TT) Groups UIC(?) Comments more effort probably required 12) Digital Filter Studies Includes determination of optimal digital filter using splitter data Groups UIC(?) Comments more effort probably required 13) Study of Sliding Windows Algorithm Includes MC study of pathologies in sliding windows algorithm, effects of including ICR energies Groups Columbia Comments more effort probably required 14) Rate and Efficiency Estimates Includes producing anticipated trigger rate vs. luminosity numbers for L1Cal triggers Groups Northeastern(?) Comments more effort probably required INSTALLATION / HARDWARE ======================= 1) TWG Includes production of multi-channel TWG Groups Fermilab 2) ADF Includes ADFs, crates, power, cable harness, hardware testing at production & installation Groups MSU(long term), Saclay 3) SCLD Includes SCLDs, SCLD to ADF cables, SCLR mezzanine hardware testing at production & installation Groups MSU(long term), Saclay 4) TAB/GAB/VME-SCL Includes TABs, GABs, VME/SCL cards, crates (custom + VME), power, ADF-to-TAB cables, TAB-to-GAB-cables, SCLR mezzanine hardware testing at production & installation Groups Columbia 5) Cabling Includes planning cable layout, fabrication of BLS-to-ADF extension cables & patch panel, dressing existing BLS cables, laying all required cables to Test Area and MCH1 Groups UIC Comments input from Columbia, MSU and Saclay will be required 6) Other Infrastructure Includes racks, cooling, alarms, safety Groups UIC Comments input from Columbia, MSU and Saclay will be required