RUN 2B L1CAL MEETING MINUTES 26 July, 2005 Present o Fermilab E.Aguillo, L.Bagby, E.Barberis, J.Benitez, M.Cwiok, D.Edmunds, C.Fantasia, G.Ginther, S.Lammers, M.Mulhearn, G.Pawloski, P.Renkel, A.Stone, W. Taylor, R.Unalan, D.Wood o FSU T.Adams o MSU M.Abolins, J.Biehl, D.Edmunds o Nevis H.Evans, C.Johnson, J.Parsons o Rice P.Padley (apologies to those I couldn't see) MSU: ---- o Testing ADF firmware in preparation for ADF-to-TAB tests at Fermilab - basically ready to go with this Nevis: TAB/GAB (H.Evans) -------------- o Received G-Link Receiver Test Board from Fabrication. - Assembled in house today. - Will start tests tomorrow. o Should get VME/SCL boards in next day or so - will also assemble these in house BLS-to-ADF Transition System (A.Stone) ---------------------------- o Hinged Patch Panel assemblies arrived last week - all are now here (40 + spares) - 12 to be installed in three racks on sidewalk . 1 rack already done, next 2 tomorrow - this 3-rack setup will allow to test all possible cable routing/bundling schemes o 25 Faceplates for ATCs came in yesterday - Jorge has installed these on the 12-14 good ATCs . some of the ATCs are significantly warped - the rest of these faceplates have 4 week turnaround . working on getting this reduced - some problems with size of faceplates . too big to fully populate crate . will be corrected by vendor o Warped ATCs - vendor will redo 12 of these . delivery of 75+12 ATCs by Aug. 10 - assembly by a different vendor by Aug. 15 o Patch Panel Cards - full production should arrive Aug. 15 o Final batch of Patch Panel cards are also out o Glenair test board - still going ahead with production of these - should be available next week o Transition System Testing - Jorge and Alan working on document describing strategy o L1Cal-Track patch cables and daughtercards are in hand Pulser Status (P.Renkel) ------------- o New GUI Installed online - will release it under p16.01 - doesn't (yet) work under latest code version Software Status (S.Lammers) --------------- o Using Todd's unpacker - a lot of infrastructure is set up here to help doing TT vs precision readout comparison . based on current Examine that compares current TTs w/ precision readout . some questions about what are the appropriate sampling weights to use and where to get them Simulation (W.Taylor) ---------- o Creating temporary .sim files for running simulator - these will be created later by COOR o tsim_l1cal2b is runnable now - main functionality exists - still a few trigger terms missing - also missing: L3 unpacker Level-2 ------- o Rumor is that Roger has just written a L2Cal worker o L2 studies are ongoing Test System (L.Bagby) ----------- o see slides posted off agenda o Daily "Toolbox" Meetings ongoing - 9:00am in the DAB1 lunch room - EVERYONE at Fermilab is encouraged to attend o ADF to TAB Tests - Rahmi has documented BER tests o TAB to L2/L3 - "g-link" errors have been resolved. Due to . noisy "Word Error" lines on FIC Channel 0 > fixed for one type of error by installing capacitor . bad VTM o GAB to L2 - no transmission errors detected o Power Supply Monitoring using EPICS - developing a GUI for this ADM Meeting Report (M.Mulhearn) ------------------ o see slide Meetings -------- o Proposal: hold bi-weekly Monday meetings - 1:00 pm in the Far Side - out of sync with bi-weekly Tuesday meetings - Hal will advertise these as well as the Tuesday meetings