Spectrometer TaskList
People:
  • Miroslav Helbich (MH)
  • Stathes Paganis (SP)
  • Bill Schmidke (BS)
  • Allen Caldwell (AC)
  • Frank Sciulli (FS)
  • Jan Hauschildt (JH)
  • Xiang Liu (XL)
  • Karina Loureiro (KL)
  • HARDWARE TASKS

    SPECTRO TASKS
    DESCRIPTION
    PERSON - TIME OF COMPLETION
    BPC Modifications
    Construction of new WLS for the BPCs Design WLS JS
    Produce WLS HERA
    Test WLS MH
    BPC south disassembly Not needed
    Shave off Tungsten plate, Frame modification. JH, HERA
    BPC reassemble Assembly jigs, stand. JH+all
    Photomultipliers Inventory (PMTs and bases)
    Definition of PMT testing procedure, Inventory of equipment needed. Simple DAQ setup in the lab. XL, KL
    Mechanical Issues
    Stand that holds BPCs Construction, Installation HERA machine group
    Collimator Design MC studies, Construction, Installation. SP, XL
    Magnet Installation, B field measurements. HERA, SP
    Proton pipe modification HERA
    Proton pipe window HERA, SP
    Helium Bag Designed for minimum e crossing. HERA, SP
    Alignment and Surveying HERA, SP
    Calibration and Monitoring
    PMT calibrations LED system (setup and test the system) MH, SP
    Energy scale calibration using the spectrum endpoint. MH, SP
    Arrange for the LED pulse to come to the Tunnel from the hole. MH, SP
    Electronics
    Cracow RO Electronics SP
    High Voltage
    Power PC SP, MH
    Data Format SP, MH


    SOFTWARE TASKS


    System Software FPGA programming MH, SP
    VME module programming MH, SP
    Slow Controls MH, SP
    PC Software Algorithms to calculate Lumi MH, SP
    Offline Software Monte Carlo SP, MH
    Acceptance Calculation using MC SP, MH
    Calibration All
    Background Studies All
    Pile-up Correctrions All