Spectrometer Task List

People:
Columbia:
  • Miroslav Helbich (MH)
  • Stathes Paganis (SP)
  • Bill Schmidke (BS)
  • Allen Caldwell (AC)
  • Frank Sciulli (FS)
  • Yujin Ning (YN) (2002)
  • Yuanbo Zhang (YZ) (2002)

  •  

     

    Summer students:
    Keewee Tan, Yuanbo Zhang, Monica Skoge, Ann Smith (2001)
    Karina Loureiro (2000)

    DESY:

  • Jan Hauschildt (JH)
  • Uwe Schneekloth (US)
  • See the Hardware tasks, software tasks and analysis tasks.

    HARDWARE TASKS


    TASK DESCRIPTION TIME PEOPLE STATUS
    Integrate the system with new electronics. The new electronics for the final version has to be integrated to the system and all the system has to be tested and understood. Fall 01 SP+MH+YN STARTED.
    Light test is working.
    FEE is working.
    Power up and test thedetectors in situ Put High voltage on all channels and make sure everything is working. Before Lumi All Both detectors tested. Some cables cannot hold HV and were replaced. Few channels don't respond.
    COMPLETED!
    Installation of collimators Both moving and beam collimator has to be put into the tunnel and positioned wrt photon beam. Special adjustable platform has to be built. May 2001 JH+MH+BS COMPLETED!
    Exit window installation Measure exit window thickness, position survey mark and install window in the tunnel March 2001 US Window thickness measured ( results ). 
    COMPLETED!
    Magnet Installation Installation of magnet into the hall 16.March 2001 US+all COMPLETED!
    Detector support structure design, construction, shielding, manufacturing and installation Until
    2.May 2001
    SP, MH, JH Designing Ready!
    Construction COMPLETED!
    Support structure on place!
    Spectrometer Detector installation Put detectors in the tunnel, limited by crane operation scheduling 26.March 2001 all  Detectors are in place! 
    COMPLETED
    Position surveying Alignment of window, collimator, magnet and LSD's need to be known to 0.3 mm August 2001 MH, US Designing Specifications. Surveying will be done by DESY survey group. Window surveyed. Magnet surveyed.
    COMPLETED!
    Electronics infrastructure Cables, connectors, general tunnel operations - Jim Crittenden COMPLETED!
    Beam Collimator Design, construction, installation 2.May 2001(?) MH, JH  Design ready. Construction COMPLETED!
    Calibration (moving) collimator Design, construction, installation Before position survey? BS, MH COMPLETED!
    Table for moving collimator  Table, electronics, slow control 2.May 2001 BS Aluminum platform ready in the tunnel.
    Table from 35m tagger is used. Table installed and connected to slow control.
    COMPLETED!
    High Voltage  Installation and testing.  8.May 2001 SP + MH+student HV cables put under the floor. Broken cables identified. 10 spare cables put under the floor. 
    Should we change all the cables?
    All cables changed. HV boxes and Communication boxes repaired an NIKHEF. System is now working.
    COMPLETED!
    New LED system interface ? ? SP  Light distribution system tested for both LSDs and proven to work.
    Automatization and testing in situ not started yet.
    COMPLETED
    Examine and test the possibility of by-passing the FEE Pulses from LSD's are narrow even after propagating in the cable and integrated charge is linear in energy down to 45ns gate as measured in the test beam ? ? Progress
    Radiation monitors Location, readout, installation, calibration, monitoring Until 
    July -August 2001
    MH + W.Wierba+student Design of prototype ready. Construction of two prototype modules in progress.

    Temporarily the PRLs were placed in the spectrometer area. 

    Cooling of collimator and magnet Design and installation 2.May 2001 HERA COMPLETED
    Electrical connection of magnet  - 2.May 2001 HERA COMPLETED
    Operation of magnet Discuss with HERA people ? ? COMPLETED
    (see faq)
    BBL3 Specify the system of alarms and interlocks required by spectrometer May 2001 MH + all COMPLETED
    Helium Bag Manufacturing and installation od bag and gas system 2.May 2001 SP, DESY(?) Gas system installed. 
    Helium bag installed.
    Bag geometry is not satisfying. Gas system has problems.

    SOFTWARE TASKS

    TASK DESCRIPTION TIME PEOPLE STATUS
    Data taking Take the first data Spring 2002 MH,SP Started
    Light tests  Write a small program to monitor the LED initiated response of the spectrometer. Spring 2002 YN,MH In progress
    Charge tests Write a small program to analyze the response of the charge test and pass the calibration information to calibration in FPGAs. Spring 2002 YN In progress
    DAQ  Test the new DAQ and implement the luminosity calculation code. Spring 2002 MH,SP Started
    GEANT Make geant to work for production. Summer 2001 SP, YZ In Progress.
    Some data form Geant already generated. Modifications done by YZ?
    LumiFast  Fast simulation for the spectrometer. Fall 2001 MH  COMPLETED!
    Slow control and Software - Summer 2001 all + Wojtek and Tomas COMPLETED!
    Algorithms to calculate Luminosity Specification of needed data, development and implementation of algorithms Summer 2001 all Started
    Online Histogramming Root, QT, QT +Root
    Developement + testing
    Summer 2001 SP + MH Simple test version in Root is working.
    QT based display from Tomek and Wojtek working.
    Test the whole Analysis software chain with mock data Use data form Geant and Test Beam for testing and debugging the software Summer 2001 SP + MH Not started yet
    Define the trigger board types and counters for spectrometer _ ASAP SP+all COMPLETED!

     

    STUDY OF LUMI RECONSTRUCTION ALGORITHMS

    TASK DESCRIPTION PEOPLE STATUS
    Acceptance calculation  Calculate spectrometer acceptance using GEANT students LumiFast simulation finished
    Exit window studies Study conversion probability in the exit window. Study effects of secondary interactions inside the window. Keewee + MH COMPLETED!
    Algorithms to calculate Luminosity Specification of needed data, development and implementation of algorithms all In Progress
    Systematic error studies Stability of the luminosity measurement against various factors has to be examined in order to be able to assign error on the measurement. MH+all In progress
    In situ alignment of the system Luminosity calculation is sensitive to relative alignment of the exit window, collimators, magnet and the detectors to the photon beam. Few in situ methods has been proposed and are in investigation phase. MH+Yuanbo Started
    Energy calibration Energy calibration will be done by use of the moving collimator with 2mm slit in it. Measurement of end-point spectrum of bremstrahlung photons will cross-check the calibration. MH+all Started
    Pile-up correction function Correction for pileup has to be applied in order to get corrected rates. The correction function will be studied by GEANT. MH Fast simulation studies ready.
    Smearing function In order to unfold measured profiles we need smearing function S(x,y,E,xg,yg,Eg) as a probability to reconstruct x,y,E given xg,yg,Eg of the photon hitting the exit window.
    This study requires to wotk with GEANT.
    ? Not started yet
    Magnetic field  Magnetic field has been measure at few points. The goal is to interpolate measurements between the points and with the help of Maxwell equations calculate other two components of the field. Errors due to interpolations seem to be non-negligible and have to be studied. In addition proton beam-pipe shielding has been moved since measurements. The corresponding change will be calculated using program OPERA.  Monica + MH+YN COMPLETED!

     
     
     
  • Click here to see old summer 2000 task list

  •  

     
     